Assembly at SmartLam

We are continuing the project at the customer's site at a good pace, with mechanical and electrical installation underway and programmers already at work.
Mechanical and electrical assembly of the Stratoplan super planer has been completed and programming started in April.
The focus of the mechanical and electrical assembly is currently on the both multi-layer storages and on the presses Rotopress and Flexipress.


Last week (Week 15) we reached the peak of the number of people working on the project, with a total of 34 people on site, including mechanics, electricians, programmers, project coordinators and designers.
Mechanical assembly is expected to be completed in June, and most of the equipment has already been shipped, with the exception of the XXL-Cut saw.